01Services02Case studies03About us04Blog 05Contact Versione italiana
ASTRI telescope at the Teide observatory under the Milky Way, with a comet and the volcano behind
Astrophysics · Complex electromechanical systems

ASTRI and SST Cherenkov telescopes

Control software, power panels and automation of the gamma-ray telescopes of the Cherenkov Telescope Array: six ASTRI telescopes installed at the Teide Observatory and more than 35 SST telescopes under construction for the southern site in Chile.

< 0.07″
Motion precision
50+
Brushless axes per telescope
OPC UA
Communication between controllers
TwinSAFE
Functional safety integrated in the controller
00

The programme

Cherenkov telescopes observe very-high-energy gamma rays and will be part of the Cherenkov Telescope Array, the international observatory for gamma-ray astronomy.

For the ASTRI Mini-Array programme six telescopes with a 4.5-metre primary mirror were built, installed and accepted at the Teide Observatory in Tenerife. More than 35 further SST telescopes are under construction for the southern CTAO site in Chile.

ASTRI telescope installed at the Teide Observatory, with technicians working at the base
Installation at the Teide Observatory
01

Control and automation

Each telescope is run by a Local Control System (safety, motion control, maintenance), integrated with the Telescope Control System that supervises structure, mirrors and Cherenkov camera. The same control system is used for factory testing and for operation at the observatory.

  • Axis control, pointing and tracking
  • Active mirror positioning, with over 50 brushless motors and patented actuators
  • Metrology to reconstruct the movements
  • Safety functions: limit switches, emergency stops and protections

The software is developed in Beckhoff TwinCAT per IEC 61131-3, in a modular, fault-tolerant architecture, with OPC UA communication between controllers and towards the upper level. Function blocks are tested on a simulator before being downloaded to the hardware.

Technician checking the drive units on the telescope base
Checking the drive units
02

Electrical panels

Power and control panels designed and wired in house, with redundant power supplies, surge protection, thermal management and identified wiring.

The operator interface has two modes. In local mode, control is enabled by a selector in the on-board cabinet, which blocks remote commands. In remote mode the telescope is commanded from the control room via SCADA, over a fibre-optic network, with cameras confirming its position.

Power panel being wired, with protection devices, power supplies and I/O modules
Power panel during wiring
03

Acceptance and commissioning

  • Factory and on-site acceptance plans: electrical checks, functional and safety tests, final acceptance
  • Electromagnetic compatibility tests on the complete telescope, in the factory
  • More than 250 design requirements and more than 100 performance requirements verified
  • CE marking under the Machinery Directive (ASTRI)
  • Dismantling, shipping and on-site reassembly by teams of electrical technicians and mechanical fitters
Telescope under test in the factory, with the control cabinets open at the base of the mirror
Factory testing, control panels open

Looking for these capabilities?