The three skids in the workshop: pumping unit with stainless steel tank and manifold with the sixteen instrumented lines
Nuclear fusion · Process plants and instrumentation

Cooling skids for the MAST-U tokamak

Three skids for the demineralised water circuit that cools a Neutral Beam Injector: pumping, filtration, regulation and flow measurement on sixteen independent lines.

3
Skids delivered as complete packages
16
Flow measurement and regulation lines
750 l
Stainless steel tank
18.6 barg
Hydrostatic test with no pressure drop
00

The circuit

MAST Upgrade is a spherical tokamak for nuclear fusion research. Its Neutral Beam Injector uses a dedicated demineralised water circuit, split across three skids.

  • Pumping skid: 750-litre stainless steel tank, three vertical multistage pumps with Y-strainers, expansion vessel, pneumatic control valves, safety valves, 4-20 mA flow meters and automatic flow control valve
  • Supply and return manifold: a DN100 flange distributes the flow across sixteen lines; on the return each line has a flow meter, balancing valve, isolation valve and thermocouple
  • A smaller measurement manifold
Pumping skid seen from the front, with stainless steel tank, vertical multistage pumps and junction boxes
Pumping skid
01

Control, instrumentation and wiring

  • Pressure or flow control and temperature control
  • Flow, pressure and temperature instrumentation
  • Pneumatic control valves
  • Junction boxes with DIN-rail terminal blocks
  • Cable routing and signal identification

Factory functional tests included a point-to-point check of the sensor signals, energising the pneumatic circuit and operating the valves.

Open junction box with power supply, protection devices and DIN-rail terminal block
Junction box on DIN rail
02

Welding, inspection and testing

  • Piping spools in 304L stainless steel, materials certified EN 10204 3.1
  • Welding documentation approved by a third-party body
  • 100% non-destructive testing on the welds: visual, dye penetrant and radiographic
  • Hydrostatic tests on the components with a 30-minute hold and no pressure drop
  • Service test on the three assembled skids at design pressure
  • Dimensional inspection of every component
Engraved marking on the header of the hydrostatic test passed at 18.6 barg
Hydrostatic test marking
03

Cleaning and traceability

Spools degreased and flushed internally, welds pickled and passivated, surfaces and flanges protected until delivery. Every component carries a number linking it to the drawing and to the material and test certificates.

Skid nameplate with design and operating pressure and temperature
Nameplate